The ORQESTRA project is organised around a set of activity pillars that guide it from coordination and design through implementation, validation, and impact.
The project began 01/12/2025 and will end 31/11/2028 (Total duration: 36 months)

These activity pillars are structured as follows:

  1. Central coordination and technical management
  2. Requirements analysis, functional specification, and architectural design
  3. Post-quantum cryptosystem design and cryptanalysis
  4. Software–hardware co-design and implementation of post-quantum cryptographic ensembles
  5. Dynamic Quantum-Key Networking in zero-trust programmable infrastructures
  6. End-to-end integration of the ORQESTRA framework, supported by use-case demonstration and evaluation
  7. Dissemination, standardisation efforts, exploitation pathways, and impact generation